Nuclear Regulatory Commission.
Opportunity to comment, request a hearing, and petition for leave to intervene.
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an amendment to Combined License No. NPF-92, issued to Southern Nuclear Operating Company, Inc. (SNC, the licensee), for operation of the Vogtle Electric Generating Plant (VEGP), Unit 4. The proposed license amendment would add a Note to VEGP, Unit 4, Technical Specification (TS) 3.7.6, “Main Control Room Emergency Habitability System (VES),” Action, Condition F to allow a one-time allowance to provide time to repair VES bottled air system valve leakage. More specifically, the proposed Note would allow a one-time 72-hour delay for the initiation of Required Actions F.1 and F.2 Completion Times for VES air system leakage repairs.
Submit comments by June 16, 2025. Request for a hearing or petitions for leave to intervene must be filed by July 14, 2025.
You may submit comments by any of the following methods; however, the NRC encourages electronic comment submission through the Federal rulemaking website.
- Federal rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-0085. Address questions about Docket IDs in Regulations.gov to Bridget Curran; telephone: 301-415-1003; email: [email protected]. For technical questions, contact the individual listed in the For Further Information Contact section of this document.
- Mail comments to: Office of Administration, Mail Stop: TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting comments, see “Obtaining Information and Submitting Comments” in the SUPPLEMENTARY INFORMATION section of this document.