Northern States Power Company; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense

3 weeks ago 1

On July 21, 2023, Northern States Power Company filed a relicense application for the 1.2-megawatt White River Hydroelectric Project No. 2444. On September 23, 2024, Commission staff issued a notice of intent to prepare an Environmental Assessment (EA) to evaluate the effects of relicensing the project.[1] The notice included an anticipated schedule for issuing the EA.

By this notice, Commission staff is updating the procedural schedule for completing the EA. The revised ( printed page 23677) schedule is shown below. Further revisions to the schedule may be made as appropriate.

Any questions regarding this notice may be directed to Nicholas Ettema by telephone at (312) 596-4447, or by email at [email protected].

Milestone—Target Date

Issue EA—August 4, 2025

Dated: May 29, 2025.

Debbie-Anne A. Reese,

Secretary.