Louisiana LNG Infrastructure LLC, Driftwood Pipeline LLC; Notice of Request for Extension of Time

1 month ago 2

Take notice that on May 13, 2025, Louisiana LNG Infrastructure LLC (Louisiana LNG) and Driftwood Pipeline LLC (Driftwood Pipeline) (collectively, the Applicants) requested that the Commission grant an extension of time, until December 31, 2029, to construct and place into service its Woodside Louisiana LNG Project (Project) located in Evangeline, Acadia, Jefferson, Davis, and Calcasieu Parishes, Louisiana as authorized in the Order Granting Authorization Under Section 3 and 7 of the Natural Gas Act (Order).[1] The Order required the Applicants to complete construction of the Project and make it available for service within seven years of the date of the Order, or by April 18, 2026.

On February 15, 2024, the Commission granted the Applicants an extension of time, until April 18, 2029, to complete construction of the Project and make it available for service.[2]

Since April 4, 2022, the Project has been actively under construction. On April 29, 2025, Woodside Energy Group Ltd announced that it had made a positive final investment decision for the foundation development of the Project, which includes the first three liquefaction trains and common infrastructure. The Applicants and Bechtel Energy Inc. have determined a minor extension of time is required in order to support additional equity sell-downs, as well as offtake agreements and other agreements with third parties to progress the development of the Project.

This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on the Applicants' request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (NGA) (18 CFR 157.10).

As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for NGA facilities when such requests are contested before order issuance. For those extension requests that are contested,[3] the Commission will aim to issue an order acting on the request within 45 days.[4] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[5] The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act (NEPA).[6] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[7] The Director of the Office of Energy Projects, or his or her designee, will act on all of those extension requests that are uncontested.

In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( https://www.ferc.gov). From the Commission's Home Page on the internet, this information is available on eLibrary. The full text of this document is available on eLibrary in PDF and Microsoft Word format for viewing, printing, and/or downloading. To access this document in eLibrary, type the docket number excluding the last three digits of this document in the docket number field.

User assistance is available for eLibrary and the Commission's website during normal business hours from FERC Online Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at [email protected], or the Public Reference Room at (202) 502-8371, TTY (202) 502-8659. Email the Public Reference Room at [email protected].

The Commission strongly encourages electronic filings of comments in lieu of paper using the “eFile” link at http://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy which must reference the Project docket number.

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, community organizations, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or [email protected].

Comment Date: 5:00 p.m. Eastern Time on May 30, 2025.

( printed page 21770)

Dated: May 15, 2025.

Carlos D. Clay,

Deputy Secretary.

Read Entire Article